BVES - Bear Valley Electric Service

California Utility Interconnection & net metering rules
Net Metering Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
0
Post Solar Billing Method
Export Rate
Solar Export Type
Fixed kWh
Solar Export Rate
0.07
Solar Export Value Notes
Per: https://www.bvesinc.com/media/managed/dgswebpagematerial05012020/DGS_Tariff_March_2020.pdf
Rebates Offered
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Size Justification
Load Justification
System Offset Notes

Systems should be sized to offset no more than the customer’s historical 12-month usage. If the customer has not acquired at least 12 months of past usage, or in cases where historical load cannot be determined due to extensive remodeling, the Load Justification Form must be submitted for systems 5 KW or greater. For systems without 12 months of historical data that are less than 5 KW, on-site electrical load may be determined using the calculation of 2 watts per square foot of the home.

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Meter Spot Process

**Go onto the website https://www.bves.com/forms/psr-application , and fill out the preliminary service request form. **


**Planner: staff )**


**Coordinator for disco: **

Allowed Meter Adapter
None

Plans & docs

SLD Reqs

Make sure the one-line diagram and equipment list identify the required manual disconnect equipment identified in Rule 21 (D) (1) (e). The manual disconnect must be located near but not inside your electric service panel. (Note: Use of any type of breaker switch in your electric panel for this purpose is not permitted.)

Electric Service Reqs

**BVES will no longer allow customers to install their solar systems directly to a sub-panel, due to safety concerns and EUSERC requirements.**


**BVES Requires a Zero Export Device to be installed so the customer can stay on the grid and receive the benefits of their solar. **

Install Reqs


Placards

BVES _**requires**_ that the electric service panel, AC disconnect and DC disconnect (when applicable) be labeled with plaques that meet the following requirements:


* Red, hard plastic and permanently affixed

* White engraving that is clearly legible

* Cautionary language


**Electric Service Panel Requirements and Example:**


1. Diagram of the structure on which the generation device is located

2. Language denoting all electric power sources on or in the premises

3. See example: Service Panel Plaque (https://www.bves.com/media/managed/nem/ElectricServicePanelCropResize.jpg)


**AC Disconnect Requirements and Example:**


1. Nominal operating AC voltage

2. Nominal operating AC frequency

3. Maximum AC power

4. Maximum AC current

5. Maximum overcurrent device rating for AC module protection

6. See example: AC Disconnect (https://www.bves.com/media/managed/nem/ACDisconnectCropResize.jpg)


**DC Disconnect Requirements and Example:**


1. Open circuit voltage

2. Operating voltage

3. Maximum system voltage

4. Operating current

5. Short circuit current

6. Maximum power

7. See example: DC Disconnect (https://www.bves.com/media/managed/nem/DCDiconnectCropResize.jpg)

Equipment Approvals
California Energy Commission
Rate Schedule Link
link
Website
link
Phone
(800) 808-2837

Other details

Restrict Inspection
0
Address ID
108036
Express Planset Eligible
Yes