First Electric Coop

Arkansas Utility Interconnection & net metering rules
Net Metering Allowed0
NEM TypeN/A
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1

Net metering & export

Net Metering Allowed
0
NEM Type
N/A
Post Solar Billing Method
Export Rate
Net Excess Generation Notes

For net metering facilities installed after September 29, 2024 (non-legacy net-metering), net metering customers will be given credit at the avoided cost of energy for any excess kWh fed back to the cooperative during the billing period.


For net metering facilities interconnected before September 30, 2024 (legacy net-metering), net metering customers are given full retail rate credit (1:1) for any excess kWh fed back to the cooperative during the billing period. Any excess kWh generated by the net metering facility will reverse the kWh on the electric meter.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
1
Supply Side Taps Allowed
1
Line Taps Allowed
1
Load Taps Allowed
1
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
25
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes

The net metering facility must have a generating capacity of no more than 25-kW or 100% of the highest monthly usage in the previous 12 months for residential use or 1,000-kW for any other use.

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Meter Spot Process

If a temporary disconnect of First Electric’s service is required for this installation, please have the homeowner call them to make this request. Homeowners will need to provide the date and approximate time that the disconnect is desired. If the name and phone number of the licensed electrician that will be on-site is available, please provide that information as well. This request should be made at least 2 days before the desired temporary disconnect. Cutting meter seals and/or the pulling of First Electric meters by anyone other than First Electric personnel can result in a tampering charge being applied to an account.

Allowed Meter Adapter
None

Plans & docs

Electric Service Reqs

Transformer Upgrades : This is part of the application review process. If required Forever can make a request for the cost estimate if you intend to pay for the necessary upgrades. If the upgrades will be the homeowners responsibility, they will need to call and request the cost estimate which would then be sent to them with instructions for payment.

Install Reqs


Equipment Approvals
California Energy Commission
Website
link
Phone
(800) 489-7405

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
694625
Express Planset Eligible
Yes