Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

County of Pierce (WA)

Washington Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE (IBC)

2021 INTERNATIONAL RESIDENTIAL CODE (IRC)

2021 INTERNATIONAL MECHANICAL CODE (IMC)

2021 INTERNATIONAL PLUMBING CODE (UPC)

2021 INTERNATIONAL FUEL GAS CODE (IFGC)

2021 INTERNATIONAL ENERGY CONSERVATION CODE (IECC)

2021 INTERNATIONAL EXISTING BUILDING CODE (IEBC)

2021 INTERNATIONAL SWIMMING POOL AND SPA CODE (ISPSC)

2023 NATIONAL ELECTRICAL CODE (NEC)

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
0
New Planset Required For Module Swap
0

Fire setbacks

Fire Setback Enforced
1

Structural & loads

Wind Speed
110
Wind Notes

https://hazards.atcouncil.org/#/

Snow Load
25
Reducible Snow Load Allowed
0
Max Attachment Spacing
96

Electrical

Allowed POI
Meter Adapter,Load Side Taps,PV Breaker,Line Side Taps
Supply Tap Neutral Ground Bond Required
1

Plan set

Plan Set Requirements


For all Trenches

  • 2 Disconnects required - one at each end of trench
  • Required for AC or DC trenches
Cover Page

Wind speed and snow load need to be shown on cover page

Electrical Diagram

For all Line Side Connections:

  • Neutral and ground bonded in fused disconnect
  • #6 bare copper run from N/G bar to (E) MSP's GEC and crimped
  • Schedule 80 PVC must be used in between fused disconnect and MSP - only showing 2 hots and neutral
  • All other conduit can be EMT

For all Load Side Taps:

  • Schedule 80 PVC must be used in between disconnect and MSP

If 2 Main service panels are present on site then both Main service panels need to be shown on ELD. If only 1 main service panel is present on site then the utility meter needs to be labeled as CL320 or CL200 meter base

Label Page


Custom Placards Required
0
Non Standard Revision Requirements

2x2 framing on Manufactured home will require a manufactured home performance verification certificate that we request from 3rd party structural engineer

Ground mount

Ground Mount Notes
  • Add note to the site plan: Dig alert (811) is to be contacted and compliance with excavation safety in accordance with government code 4216 will be followed, prior to any excavation taking place.
  • Provide structural details\calculations for the footings and components of the ground mount design.
  • Provide conduit/conductor, type, size, and length for all underground sections.
  • Add note: Ground Mount Structure to be grounded per (CEC 250). ELECTRICAL SYSTEM
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Pierce (WA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.