County of Nelson (VA)

Virginia Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 VIRGINIA UNIFORM STATEWIDE BUILDING CODE

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL PLUMBING CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL SWIMMING POOL AND SPA CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL FUEL GAS CODE

2021 INTERNATIONAL FIRE CODE

2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
2
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes
Wet Stamps Required
Digital Structural,Digital Electrical
Structural Calculations Required
Yes
Ee Stamp Notes
Need Letter from Electrical Engineer to verify system compliance
Stamp Location On Plans
Unspecified

Fire setbacks

Fire Setback Enforced
1
Setback Notes
Standard

Structural & loads

Wind Speed
115
Snow Load
30
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Meter Adapter,PV Breaker,Load Side Taps,Line Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
Standard
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Custom Placards Required
1
Placards Notes
POST THE PERMIT CARD IN A CLEARLY VISIBLE LOCATION FROM THE ROAD PRIOR TO REQUESTING THE FIRST INSPECTION. A COPY OF THE PERMIT IS REQUIRED BY 13VAC5โ€63โ€100, SECTION 110.5 TO BE POSTED AT THE JOB SITE FOR PUBLIC INSPECTION. THIS ASSISTS TRADE WORKERS IN REQUESTING THE CORRECT PERMIT INSPECTION AND INSPECTORS TO IDENTIFY THE SITE

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Nelson (VA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.