Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

County of Wasatch (UT)

Utah Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
SolarAPP+ StatusNot accepted
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE 2021 INTERNATIONAL RESIDENTIAL CODE 2021 INTERNATIONAL MECHANICAL CODE 2021 INTERNATIONAL PLUMBING CODE 2021 INTERNATIONAL FUEL GAS CODE 2021 INTERNATIONAL ENERGY CONSERVATION CODE 2021 INTERNATIONAL EXISTING BUILDING CODE 2021 INTERNATIONAL SWIMMING POOL AND SPA CODE 2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Not accepted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category C

Snow Load
45
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Meter Adapter,Line Side Taps,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

TPW required to be inside due to low temperatures

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

PV Systems with batteries are required to be stamped and signed by an Electrical Engineer. Please review the PV Plan Check document uploaded to your files to be sure that you have all of the documents required

Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Wasatch (UT) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.