Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

City of Springville (UT)

Utah Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE 2021 RESIDENTIAL BUILDING CODE 2021 INTERNATIONAL PLUMBING CODE 2021 INTERNATIONAL MECHANICAL CODE 2021 INTERNATIONAL FUEL GAS CODE 2021 INTERNATIONAL ENERGY CONSERVATION CODE 2021 INTERNATIONAL EXISTING BUILDING CODE 2021 INTERNATIONAL FIRE CODE 2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
90
Wind Notes

Exposure Category C

Snow Load
35
Reducible Snow Load Allowed
1
Max Attachment Spacing
48
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Meter Adapter,Line Side Taps,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

Utah does not want single panel arrays with railless systems. Please have layout changed if this happens Include photos of the existing MSP and the roof structure.

Attachment Detail

No single panel arrays 48'' max attachment spacing

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Springville (UT) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.