County of Collin (TX)
NEC Code Version2011
Wet Stamps RequiredNone
Fire Setback Enforced0
Codes
- NEC Code Version
- 2011
- Code List
NFPA 101 LIFE SAFETY CODE 2009 INTERNATIONAL BUILDING CODE 2009 INTERNATIONAL FIRE CODE 2009 INTERNATIONAL MECHANICAL CODE 2009 INTERNATIONAL PLUMBING CODE 2011 NATIONAL ELECTRIC CODE 2009 INTERNATIONAL FUEL GAS CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 1
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- None
- Structural Calculations Required
- No
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 90
- Wind Notes
Exposure Category B
- Snow Load
- 5
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- Roof mount projects - NO permits Ground mount projects require a permit
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Line Side Taps,Meter Adapter,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- No
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Roof mount projects - NO permits Ground mount projects require a permit
- Electrical Diagram
Standard
- Custom Placards Required
- 1
- Placards Notes
Need placard on every job per utility.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
Permit/plan check required for ground mount projects need to provide drawings of the septic system showing the spray heads in comparison to their home that are stamped by a "Registered Sanitarian" - see a past project
- Ground Mount Requires Soil Sample
- Flood Study