City of Rockwall (TX)
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL PLUMBING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2020 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 1
- Rough Inspection
- Rough Electrical
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 115
- Wind Notes
Exposure Category B
- Snow Load
- 5
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
**AHJ requires Structural plans designed and sealed by a Texas Professional Engineer for securing the panels to the existing structure or to a new foundation or structure shall be submitted.**
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,PV Breaker,Line Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
- If battery location is susceptible to vehicle damage, must install bollards to prevent damage per NFPA 855 Must install interconnected heat or fire detector in area of storage system per NFPA 855 Must have 3ft of separation or provide manufacturer specifications for minimum separation per NFPA 855
- Inspectors want to see mounting hardware screws landed to a stud not brick. Inspectors of the city of Rockwall say that the brick is just a veneer and that screws should embed into stud
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim