County of Curry (OR)
NEC Code Version2023
Wet Stamps RequiredNone
Fire Setback Enforced0
Codes
- NEC Code Version
- 2023
- Code List
2021 OREGON RESIDENTIAL SPECIALTY CODE
2019 OREGON STRUCTURAL SPECIALTY CODE
2019 OREGON MECHANICAL SPECIALTY CODE
2021 OREGON PLUMBING SPECIALTY CODE
2023 OREGON ELECTRICAL SPECIALTY CODE
2025 OREGON ENERGY EFFICIENCY SPECIALTY CODE
2019 OREGON ZERO ENERGY READY COMMERCIAL CODE
2019 OREGON FIRE CODE
2010 OREGON MANUFACTURED DWELLING INSTALLATION SPECIALTY CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- None
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 999
- Snow Load
- 999
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Electrical Diagram
- Electrical through County of Coos (OR). Please see the database for electrical design requirements.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim