NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback EnforcedYes

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2024 OHIO BUILDING CODE (2021 IBC)

2019 RESIDENTIAL CODE OF OHIO (2018 IRC)

2024 OHIO EXISTING BUILDING CODE (2021 IEBC)

2023 OHIO ELECTRIC CODE (2023 NFPA 70)

2021 INTERNATIONAL FIRE CODE (IFC)

IEBC Accepted
Yes
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
Yes
New Planset Required For Module Swap
No

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes - Multiple Layer Shingle
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
Yes

Structural & loads

Wind Speed
115
Snow Load
20
Reducible Snow Load Allowed
Yes
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
No
ESS Elevation Detail Required
No

Plan set

Roof Plan

INDICATE HOW MANY LAYERS THE ROOF HAS

Electrical Diagram


Electrical Diagram Notes

All Jobs [CONDUIT FILL AND WIRE SIZED PER NEC CODE]

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Ground Mount Notes
  • Max height 16 feet.
  • Panels only allowed in the rear yard.
Setback Back Yard
5
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Monroe (OH) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.