City of Cleveland (OH)
NEC Code Version2023
Wet Stamps RequiredDigital Structural
Fire Setback Enforced0
Codes
- NEC Code Version
- 2023
- Code List
2024 OHIO BUILDING CODE (2021 IBC)
2019 RESIDENTIAL CODE OF OHIO (2018 IRC)
2024 OHIO EXISTING BUILDING CODE (2021 IEBC)
2023 OHIO ELECTRIC CODE (2023 NFPA 70)
2021 INTERNATIONAL FIRE CODE (IFC)
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 0
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 90
- Snow Load
- 20
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
Documents to be properly sealed by the engineer of record
- Minimum Ground On Roof
- #10
Electrical
- Allowed POI
- PV Breaker,Load Side Taps,Line Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim