New Mexico Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Wet Stamps RequiredDigital Structural
Fire Setback Enforced0

Codes

NEC Code Version
2020
Code List

2018 INTERNATIONAL BUILDING CODE 2018 INTERNATIONAL RESIDENTIAL CODE 2018 INTERNATIONAL FIRE CODE 2018 INTERNATIONAL ENERGY CONSERVATION CODE 2018 INTERNATIONAL EXISTING BUILDING CODE 2018 INTERNATIONAL FUEL GAS CODE 2018 INTERNATIONAL MECHANICAL CODE 2018 INTERNATIONAL PLUMBING CODE 2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural

Fire setbacks

Fire Setback Enforced
0
Setback Notes
Standard

Structural & loads

Wind Speed
999
Snow Load
15
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Meter Adapter,Line Side Taps,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
Standard
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements
Our PM and AC disco has be within 5 ft of the UM and add an additional disco on the exterior of the home Interconnection and Net Metering Rules: Rule 17.9.568 covers interconnections for qualifying and non-qualifying facilities as large as 10MW Rule 17.9.570 provides guidelines for metering and billing for qualifying facilities. The New Mexico Interconnection Manual Comply With: NFPA 70: National Electric Code, NEC New Mexico Administrative Code Title 14, Chapter 10: New Mexico Electrical Code City of Truth or Consequences Building Code No Rec Meter is required
Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Truth or Consequences (NM) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.