Borough of Somerville (Somerset County) (NJ)
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL PLUMBING CODE
2020 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 3
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Wet Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 85
- Snow Load
- 999
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
When panels are on the front of the home, a signed and sealed letter explaining why the panels are front facing is required.
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- PV Breaker,Meter Adapter,Line Side Taps,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Roof Plan
1. AHJ has policy regarding panels installed in the front of a customer's residence. A stamped letter from Design will be required for projects that have panels in the front of the customer's house. See link below for further information specifically point E 1. AHJ Zoning official stated that he wanted the streets labeled by the customer's home to determine which is the front roof plane of the customer's home. He specifically stated this in the event if the customer has a corner lot which would then create an issue of (2) front roof planes.
- Electrical Diagram
If lineside tap (LST), then a Hoffman Tap Box (junction box) is required.
- Electrical Diagram Notes
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim