NEC Code Version2020
SolarAPP+ StatusTargeted
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback EnforcedNo

Codes

NEC Code Version
2020
Code List

2015 INTERNATIONAL RESIDENTIAL CODE 2015 INTERNATYIONAL BUILDING CODE 2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
Yes
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
1
Revision Required
No
New Planset Required For Module Swap
No

Stamps

Ee Stamp Required On SLD
Yes
Wet Stamps Required
Digital Structural,Digital Electrical
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
No
Setback Notes

3' sid

Structural & loads

Wind Speed
130
Snow Load
10
Reducible Snow Load Allowed
Yes
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Allowed POI
Load Side Taps,Meter Adapter,Line Side Taps,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
No
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Ground mount

Ground Mount Fencing Required
Mesh/Scrim