Town of Vassalboro (ME)

Maine Authority Having Jurisdiction Solar permitting requirements

Spot something wrong?

These change with code cycles. If a requirement here is out of date or missing, tell us and we'll fix it.

Report a correction
NEC Code Version2023
Fire Code Version2018 Building Code
Fire Setback EnforcedYes

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

MAINE UNIFORM BUILDING AND ENERGY CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL MECHANICAL CODE

2023 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
3
Revision Required
Yes
Rough Inspection
None
New Planset Required For Module Swap
No

Stamps

Structural Calculations Required
Yes

Fire setbacks

Fire Setback Enforced
Yes

Structural & loads

Wind Speed
90
Snow Load
70
Reducible Snow Load Allowed
Yes
Minimum Ground On Roof
#10

Plan set

Custom Placards Required
No

Ground mount

Ground Mount Fencing Required
Mesh/Scrim