City of Bangor (ME)
NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
MAINE UNIFORM BUILDING AND ENERGY CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL MECHANICAL CODE
2023 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
DETACHED STRUCTURES REQUIRE SETBACKS 5/2025
Structural & loads
- Wind Speed
- 115
- Wind Notes
AHJ requested for wind speed to be 115
- Snow Load
- 80
- Snow Load Notes
AHJ requested 80 psf for snow load for both ground and roof amounts
Windspeed needs to be updated to 115 but it is locked now
- Reducible Snow Load Allowed
- 1
- Structural Notes
The weight (per each roof section) of racking and panels is required on the Structural Calculation.
- Minimum Ground On Roof
- #10
Electrical
- Allowed POI
- Meter Adapter,PV Breaker,Load Side Taps,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim