Village of Romeoville (IL)

Illinois Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2015 Building Code
SolarAPP+ StatusTargeted
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2015 Building Code
Code List

2014 STATE OF ILLINOIS PLUMBING CODE

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL CONSERVATION CODE

2021 INTERNATIONAL FIRE CODE

2021 INTERNATIONAL FUEL GAS CODE

2021 INTERNATIONAL MECHANICAL CODE

2020 NATIONAL ELECTRIC CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
1
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Ridge Setback
36
Rake Setback
36
Hip Valley Setback
18
Eave Setback
18
Setback Notes

2015 IBC/IRC 3' Setback EVERY PROJECT - Add an 18 fire set back at the EAVE

ONLY 50% ARRAY COVERAGE ALLOWED

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category B

Snow Load
30
Reducible Snow Load Allowed
0
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates,Battery
Allowed POI
Load Side Taps,Line Side Taps,PV Breaker,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
75
De Rating Ampacity
1

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

*702.4 Direction*

  • AHJ Enforcing NEC 702.4 (Optional Standby Systems) for ESS Will require us to only backup essential loads whose total demand does not exceed what the # of Batteries can provide E.g., 1x Tesla PW3 can export 48A, and so the total load demand in backup cannot exceed 48A as shown on planset load calculations (standard and optional acceptable). 
  • Option 1: 702.4(B) EMS or Load Management Hardware Exception can be used in NEC 2020/2023 as to allow maximum capable backup loads (I.E.-SPAN). 
  • Option 2: 220.87(1) Exception: Load Calculation based on Utility Meter Demand Data (Green Button - 15 min Interval over a 30 day period.) 
  • Option 3: Load Calculations via Emporia Energy Monitoring (30 Day Period) 
  • Option 4: Downsize loads
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

ONLY 50% ARRAY COVERAGE ALLOWED

Site Notes

All Jobs [AC disconnect is required within sight of the inverter]

Electrical Diagram


Electrical Diagram Notes

All Jobs [MINIMUM GROUNDING CONDUCTOR MUST BE #8 COPPER WIRE // ALL CONDUIT MUST BE RMC]

Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the Village of Romeoville (IL) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.