County of Monroe (IL)
NEC Code Version2005
Fire Code Version2015 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced0
Codes
- NEC Code Version
- 2005
- Fire Code Version
- 2015 Building Code
- Code List
2005 NATIONAL ELECTRIC CODE
2006 INTERNATIONAL BUILDING CODE
- IEBC Accepted
- 0
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 90
- Snow Load
- 20
- Reducible Snow Load Allowed
- 1
- Structural Notes
SE Stamps/Calcs required
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Allowed POI
- PV Breaker,Line Side Taps,Load Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
AHJ doesn’t allow SEEB batteries to be installed outside, only Tesla batteries, due to SEEB having operational temperatures of 14 deg. while Tesla's is -4 deg.
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Electrical Diagram
- The Nema 3R disconnect switch should be adjacent to the electric meter and accessible to the servicing utility company.
- The switch must be fusible, minimum size 100 Amp, single phase or three phase and rated for service voltage.
- The switch must be securely fastened to the building structure, have a visible open gap between the switch contacts, knife-blade type.
- Fusible safety switch must include a label sta􀆟ng voltage and amperage of solar system and all addi􀆟onal labels required.
- Label Page
- Plaques must be either attached to the AC Generation Safety Disconnect or located next to the disconnect. Plaques are not allowed to be mechanically attached to the safety switch with screws, pop rivets, or similar means, as this would compromise the UL rating.
- Plaque must be a minimum of 5” x 7” in size.
- Wording for the plaque at the safety disconnect switch must state: “CAUTION: Multiple Sources of Power - Lockable AC Generation Source Disconnect.”
- If the disconnect is within 10 feet and within sight of the meter, the signage must state: “CAUTION: Multiple Sources of Power - Lockable AC Generation Source Disconnect available for Isolation from Utility.”
- Plaque must be a two-ply or three-ply, non-conductive plastic engraved plate that is weatherproof and UV resistant.
- All solar raceways/conduit installed with DC and AC conductors must be labeled every 10 feet minimum as:
- “Warning: Photovoltaic Power Source.”
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim