Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

City of Park City (IL)

Illinois Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2008
Fire Code Version2015 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2008
Fire Code Version
2015 Building Code
Code List

2009 INTERNATIONAL BUILDING CODE

2009 INTERNATIONAL RESIDENTIAL CODE

2006 INTERNATIONAL PROPERTY MAINTENANCE CODE

1996 BOCA NATIONAL FIRE CODE

1996 INTERNATIONAL MECHANICAL CODE

2008 NATIONAL ELECTRICAL CODE

2018 IECC - ILLINOIS ENERGY CODE UPDATE

IEBC Accepted
1
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
0
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes

Fire setbacks

Fire Setback Enforced
1

Structural & loads

Wind Speed
107
Wind Notes

https://ascehazardtool.org/

Snow Load
56
Snow Load Notes

https://ascehazardtool.org/

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Illinois law states that there must be a report

from a licensed structural engineer and the pertinent drawings must be sealed, signed, and

dated and expiration date of the seal by the same licensed structural engineer. This report must

attest to the structural integrity of the existing roof framing members with regard to the

appropriate spacing and quantity of array structural attachments. It also must attest to the

attachments' weather sealing detail according to building code and product installation

instruction.

Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
No
Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Load Side Taps,Meter Adapter
Supply Tap Neutral Ground Bond Required
1
Temperature Rating
90
De Rating Ampacity
0.91
BOS Restrictions

Standard

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard ESS Requirements

Separate ESS Disconnect Required
No
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

Standard

Cover Page

Standard

Site

Standard

Roof Plan

Standard

Attachment Detail

Standard

Electrical Diagram

Standard

Label Page

Standard

Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes

Standard Ground Mount requirements

Setback Front Yard
10
Setback Back Yard
5
Setback Side Yard
5
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Park City (IL) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.