City of Homestead (FL)
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2023 8TH EDITION FLORIDA BUILDING CODE: BUILDING
2023 8TH EDITION FLORIDA BUILDING CODE: RESIDENTIAL
2023 8TH EDITION FLORIDA BUILDING CODE: MECHANICAL
2023 8TH EDITION FLORIDA BUILDING CODE: PLUMBING
2023 8TH EDITION FLORIDA BUILDING CODE: FUEL GAS
2023 8TH EDITION FLORIDA BUILDING CODE: ENERGY CONSERVATION
2023 8TH EDITION FLORIDA BUILDING CODE: EXISTING BUILDING
2023 8TH EDITION FLORIDA BUILDING CODE: ACCESSIBILITY
2023 8TH EDITION FLORIDA FIRE PREVENTION CODE (NFPA)
2020 NATIONAL ELECTRIC CODE (NEC)
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- Rough Electrical
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Ee Stamp Notes
Digitally Verified Signature
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
- Provide a minimum of two 36-inch-wide roof pathways on separate roof planes from the lowest roof edge to the ridge (see exemptions).
- Provide at least one roof pathway on the street or driveway side.
- For each roof plane with PV, provide a 36-inch-wide pathway from the lowest roof edge to the ridge (same, adjacent, or straddling roof planes).
- Pathways shall support firefighter access and be located in areas with minimal obstructions.
- Ridge setback: If PV covers more than 33% of the roof area (66% if sprinklered), provide a 36-inch clear setback on both sides of horizontal ridges.
Structural & loads
- Wind Speed
- 175
- Wind Notes
Exposure Category C ; HVHZ
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
Stamp Tech Instructions:
- Send the SIF form from the Files section at the bottom of this AHJ database to the PE for completion. The AHJ will not accept documents that are modified after being signed.
PE Instructions:
- Provide SE/EE digital stamps with verifiable PDF digital signatures on all PV plan pages (typically sheets 1-7A). Complete the Florida Statute and PE Letter/Calculations sections of the SIF form. (See the form in the Files section.)
Digitally Verified Signature
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Line Side Taps,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Module spec sheets must list UL 1703 certification. Racking system specs must list UL 1703 and 2703 certifications.
- Cover Page
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim