City of Deltona (FL)

Florida Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
SolarAPP+ StatusTargeted
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2023 8TH EDITION FLORIDA BUILDING CODE: BUILDING

2023 8TH EDITION FLORIDA BUILDING CODE: RESIDENTIAL

2023 8TH EDITION FLORIDA BUILDING CODE: MECHANICAL

2023 8TH EDITION FLORIDA BUILDING CODE: PLUMBING

2023 8TH EDITION FLORIDA BUILDING CODE: FUEL GAS

2023 8TH EDITION FLORIDA BUILDING CODE: ENERGY CONSERVATION

2023 8TH EDITION FLORIDA BUILDING CODE: EXISTING BUILDING

2023 8TH EDITION FLORIDA BUILDING CODE: ACCESSIBILITY

2023 8TH EDITION FLORIDA FIRE PREVENTION CODE (NFPA)

2020 NATIONAL ELECTRIC CODE (NEC)

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
1
Revision Required
1
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes
Wet Stamps Required
Digital Structural,Digital Electrical
Structural Calculations Required
Yes
Ee Stamp Notes

FL Statute Letter Required

Digitally Verified Signature

Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

* Provide clear setbacks on both sides of the horizontal ridge. (R324.6.2) * Not fewer than two pathways, on separate roof planes from the lowest roof edge to the ride and not less thank 36 inches wide, shall be provided on all buildings

Structural & loads

Wind Speed
145
Wind Notes

Exposure Category C

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
48
Structural Notes

Digitally Verified Signature


*NEW* This AHJ has been kicking us back when engineer calls out different engineer letter information than the plans call for, ie. 2 lags vs 4 lags, embedment, etc..

*NEW* If there is any difference between what the PE calls for and the plans show, please contact designer to revise the planset to comply with what PE calls for. - SPECIFICALLY with embedment. Some plansets erroneously show 2" embedment when letter calls for 2.5" - please kick this back to the designer via. ticket or teams message to fix.

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
75
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

#NFZ_ALL#


Site Notes

**********Whenever we get a rejection rework please escalate the project to staff************

Roof Plan

Show the attachment points on roof plan.

Electrical Diagram

ALL JOBS:

  • Show wire size of utility feeders

BATTERY JOBS:

  • Provide sizes of other breakers on main service busbar

LST

  • When the POI is on the supply (line) side we must notate that the neutral and ground are bonded together


If we're utilizing SUM OF ALL BREAKERS as a POI - reflect the 2020 NEC code referencing it on your SLD with a leader to the breaker.



IX needs to be notated on plans (Ie. Compliant to Sum of all breakers... 120%... etc)


General note that states "Electrical portion shall comply with Article 250 grounding requirements"

Label Page

Special Label is required for ALL jobs for this AHJ (see Volusia County label below).

Label must match exactly in color and verbiage.

Provide label outlining installing contractors name, and emergency contact number, per section 11.12, of NFPA-1

Custom Placards Required
0
Placards Notes
N/A

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Deltona (FL) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.