Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 3
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes - 10kW+
- Wet Stamps Required
- Digital Electrical,Digital Structural
- Structural Calculations Required
- Yes
- Ee Stamp Notes
Required for projects over 10kW
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Snow Load Notes
N/A
- Reducible Snow Load Allowed
- 0
- Max Attachment Spacing
- 96
- Structural Notes
Calcs MUST show
- Rafter Size
- Embedment screw depth
- Number of modules on each mounting plane
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Standard
Utility meter cannot be underneath the patio cover
Battery / ESS
- Unique Battery Placards Needed
- 1
- ESS Notes
Battery system must be shown on placard.
ESS disconnect required within line of sight of ESS on same wall and not blocked by walls/gates/etc
- Separate ESS Disconnect Required
- Local Disconnect,ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
All Jobs - Structural calculations need to show 3/4" minimum embedment depth penetration, Module count needs to be shown Structural calculations
All HCD Riverside jobs are NOT solar app qualified
- Attachment Detail
- Attachment Detail Notes
ALL JOBS [3/4" MINIMUM EMBEDMENT DEPTH PENETRATING]
- Electrical Diagram
EE stamps required on projects over 10kW
- Custom Placards Required
- 1
Ground mount
- Ground Mount Fencing Required
- Situational
- Ground Mount Notes
Ground Mounts: Fencing requirements will be based on city jurisdiction rules. If in a park, no more than 75% of the lot can be covered with the mobile home and all accessory structures. When demonstrating the path of the trenching, use a dark color. Light greys do not show up when printed and the AHJ will reject the plans for it being missing. Depict and dimension septic tank and disposal field locations