Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

County of Santa Cruz (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 California Administrative Code

2025 California Building Code

2025 California Residential Code

2025 California Electrical Code

2025 California Mechanical Code

2025 California Plumbing Code

2025 California Energy Code

2025 California Wildland-Urban Interface Code 

2025 California Historical Building Code

2025 California Fire Code

2025 California Existing Code

2025 California Green Building Standards

2025 California Referenced Standards Code

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Date SolarAPP+ Accepted
45198
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
2
Revision Required
1
New Planset Required For Module Swap
0

Stamps

Structural Calculations Required
No

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1
BOS Restrictions

AHJ Specific Load Calculations Sheet Required: https://cdi.santacruzcountyca.gov/Portals/35/CDI/UnifiedPermitCenter/Building/Forms%20&%20Publications/PLG%20Forms/EVCS%20Electrical%20Load%20Calculation%20Single-Family_PLG290.pdf

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Railing Spec sheets and Powerwall mounting detail Spec sheets required (When Applicable)

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements
  • Per AHJ "Both racking & module pages within the plan set need to state fire Class A Type 1 or 2."(Verify that module page(s) call out fire ratings. Please slip sheet in the UNIRAC Solar Mount Racking Fire Classification PDF into the plans(attached below in the files section)
  • REMOVE QR CODE PAGE FROM PLANS - AHJ WILL REJECT QR Codes

PLAN Submission Requirements

Bookmarks

  • All sheets must be bookmarked.
  • Bookmarks must be set to Fit Page (width & height).
  • Each bookmark must include both the sheet name and sheet number.
  • All sheets must be minimum 11x17 in size.
  • No layers in the PDF - remove all layers before submitting. (Flatten PDF)
  • Use a markup color other than red - red is reserved for plan reviewers.
  • Example: “Cover Sheet - S1”

Supplemental requirements (Spec Sheets)

  • Supplemental (SUP) file must include a completed Supplemental Index PLG235 form as the front page, and have every document and section bookmarked, set to "fit page", and flattened. This will need to be uploaded separately.
Cover Page

APN parcel number must be on the cover sheet.

Electrical Diagram


Electrical Diagram Notes

All jobs [The secondary power source (PV system) shall be connected on the opposite end of the busbar as the main breaker, per 705.12(B)(3)]

Sub Panel [Re-located existing 120V, 15 & 20 amp circuits extended more than 6’ shall be protected by AFCI - CEC 210.12(D)]

Label Page


Custom Placards Required
1
Non Standard Revision Requirements


Revisions / Corrections

  • Submit the Construction Change Form PLG-205 with revision letter attached
  • List all changes in the scope of work section on the PLG-205 form.
  • Revised Plans must be by themselves, remove revision letter
  • Ensure each revised sheet has a corresponding bookmark.
  • Responses must include an annotated copy of these comments and indicate the specific sheet/drawing numbers where revisions are located for all correction comments.
  • Please use another color aside from red for markups on plan sheets. Red is reserved for plan reviewers.

Ground mount

Ground Mount Fencing Required
Yes
Ground Mount Notes

10' FREE OF VEGETATION REQUIRED

Setback Front Yard
20
Setback Back Yard
15
Setback Side Yard
10
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Santa Cruz (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.