County of Nevada (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusTargeted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

IEBC Accepted
1
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
2
Revision Required
0
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
None
Structural Calculations Required
Yes - Attachment Spacing > 2ft
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
999
Snow Load Notes

Check county GIS for project specific snow load.

Find specific parcel and click on "parcel report" snow load will be displayed on the bottom table titled "property context" varies per site location 0-70+ psf snow load

Reducible Snow Load Allowed
1
Max Attachment Spacing
24
Structural Notes
Engineering not required IF the attachment spacing is 24" on center. If attachments are spaced greater than 24" on center, follow below PE requirements. PE Requirements; SE digital stamps on corresponding PV pages & PE Letter / Calcs. WS 110 MPH
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Meter Adapter,Line Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
  • All Tesla Powerwall jobs require a Gen Panel and disconnect between Gen Panel and Gateway.
  • ESS projects must have an ESS disconnect within 3' of the main panel.
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

On the location of the AC disconnect, it should be between the batteries and the new 125amp load center. This is due to the fact that the batteries would still continue to feed the critical loads if the current disconnect on the single line diagram is used. 48 OC attachments for the entire county.

Site

ESS projects must have an ESS disconnect within 3' of the main panel.

Electrical Diagram

Standard

Electrical Diagram Notes

Battery [Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).]

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes
  • Accurately show the location of the well (if necessary) on the site plans
  • Accurately show the location of the septic system on site plan

records request for septic and plot maps = Community Development Public Records Request | Nevada County, CA

Setback Front Yard
20
Setback Side Yard
15
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Nevada (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.