County of Kern (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
Other (See Submission Notes)
Revision Required
1
Rough Inspection
Footing inspection
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
95
Wind Notes

Exposure Category B

Snow Load
5
Snow Load Notes

All elevations from 5000-6000ft have a 40 PSF snow load snow load in TEHACHAPI is 30 psf

Reducible Snow Load Allowed
1
Max Attachment Spacing
48
Structural Notes


Please provide calculations for distributed load and point load on roof sheathing

Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

RESIDENTIAL CODE 328 - PROHIBITS INSTALLATION OF TESLA POWERWALL 3 IN GARAGE

  • If a battery is located inside, the project will require heat sensors for smoke & carbon detectors
  • BOLLARDS REQUIRED IF NEAR VEHICLE DAMAGE
  • UL 9540 APPROVED
Separate ESS Disconnect Required
Gateway Disconnect,ESS Disconnect
ESS Elevation Detail Required
Yes

Plan set

Plan Set Requirements
  • Flattened Plans set - To be able to submit online (In AutoCad, on the command line, enter EPDFSHX and change the value to 0 (zero).)
  • APN needs to be on plans http://assessor.co.kern.ca.us/prop_search.php
  • Fill out Expedite Checklists provided on this AHJ page (not required if project includes a battery)
  • Complete expedite form - Residential Rooftop Solar Submittal Requirements and Checklist - rafters only
  • Building plans shall identify the proposed bottom of solar panels and all electrical equipment to be resistant to flood damage at minimum of 1.5' above highest adjacent grade
Cover Page


Site

Existing Systems:

Add existing panels to Label page.

Cloud existing system

Add note: (E) Existing solar may not be rapid shutdown Compliant

Roof Plan

AHJ Fire Setbacks have been uploaded in file section below.

 A minimum clear space of three feet is provided on the control side of roof mounted HVAC equipment.


BALLAST SYSTEMS:

Show existing roof framing on the plans. Please graphically show roof framing and location of ballast blocks in relation to framing.

Attachment Detail

Avoid using portrait orientation for Rockit attachments. If portrait orientation is required, swap to rail.

Attachment Detail Notes

Please design at 4' spacing to avoid failing inspection

Electrical Diagram
  • Zinsco panels require load calcs, per correction for Biagioni, Dwayne
  • Centerfed 120% allowed
Label Page

Provide a site roof plaque to delineate the RS & non RS arrays, if applicable

Reflective Sticker : RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM. 

Custom Placards Required
1
Placards Notes
  • All Standard Placards used for CA projects
  • 2nd/Additional Main Placard required to be installed at Battery for all ESS Jobs
  • Derate placard stating 'DERATED MAIN BREAKER - DO NOT CHANGE' installed at derated breaker for all Derates

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes
  • NUANCE DQ DUE TO SOIL REPORT AND SPECIAL INSPECTIONS REPORT
  • GM cannot be placed in the front. Setback requirements for the Side and Rear vary by zone and lot. Contact Planning.
  • septic/record requests: Open Public RecordsNextRequest - Modern FOIA & Public Records Request Software
  • GMs require 10 ft clearance around array in all cases. (Site specific property setbacks may be higher than 10ft, but 10ft is minimum clearance around array, Show on plans)
  • Show the dimensions of the array (N-S and E-W direction and array height). Must match calculations.
  • Flattened PV Plan Set - Needed to submit online
  • This note needs to be on plans for GROUND MOUNTS - THE PROPOSED BOTTOM OF SOLAR PANELS AND ALL ELECTRICAL EQUIPMENT TO BE RESISTANT TO FLOOD DAMAGE AT MINIMUM OF 2356.0' NAVD88.
  • Fencing required by AHJ
  • All  ground mounts will require site-specific engineering.
  • Soils report should not be attached to the PV Plans. We will need to submit it separately.
  • Specify on cover sheet of plans the following structural information: • Ground snow load per Section 17.06.140 of the Kern County Code of Building Regulations. • Ultimate design wind speed in miles per hour, and wind exposure. • Seismic design category (SDC) and site class.
  • Specify on plans material specifications for the following: â€¢ Concrete compressive strength
  • A clear, brush-free area of 10ft shall be required for ground mounted PV arrays
  • Show distance from array to structures on property
  • soil report and a statement of special inspections on the cover sheet, prepared by the RDP, in accordance with CBC Sec. 1704.3. for Nuance
  • Please specify on cover sheet of plans, the following structural information: • Ultimate design wind speed in miles per hour, and wind exposure. • Seismic design category (SDC) and site class. Please add a note indicating the SDC = D. Site class will be determined by the soils report. 
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Kern (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.