City of Solana Beach (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching
- How Many Plansets Required
- 3
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 1
Stamps
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- PV Breaker,Load Side Taps,Line Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
ESS disconnect required within 6ft of MSP on same wall and not blocked by walls/gates/etc
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
All projects using tilt kits will need an accompanying letter explaining why the panels must be installed on an angle rather than flush to the roof. The blank square reserved for stamps on all PV pages must be titled For City Stamps or the AHJ will reject it.
- Cover Page
- Note on the plan the utility’s available fault current.
- Provide fault current calculations. Indicate the calculated available fault current values and its corresponding withstand kAIC rating at each panel, disconnect switch, etc.
- Provide voltage drop calculations.
- Cover Page Notes
All Jobs [PV wires and/or cables shall be listed // A temperature adder of 60F (33C) shall be added to the outdoor temperature when determining ampacity correction factors for conduits installed less than 7/8 inches from the roof surface]
- Roof Plan
If junction boxes are shown on ELD, they also need to be on the roof layout.
- Electrical Diagram
When installing a new sub panel, include load calcs for the new sub panel.
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim