City of Santa Ana (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
3
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes - Derate
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Ee Stamp Notes

EE digital stamps only on Derates

Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

PE Requirements; SE digital stamps on all corresponding PV pages & PE Letter / S. Calcs. WS 110 MPH EE digital stamps only on De-Rates

For flat roofs: Special calcs are required:

Show roof rafters can take loads from the solar panel (point loads) and show connections can take uplift load (roof rafter connection to the wall)

Approved Calcs Attached below.

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
Panel Schedule Required
All Projects
Temperature Rating
75
De Rating Ampacity
0.96
BOS Restrictions

Standard

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

ESS DISCONNECT REQUIRED NEXT TO BATTERY IF IT IS NOT WITHIN LINE OF SITE OF THE INVERTER DISCONNECT

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

SYSTEM WORKSHEET AND PERMIT EXPEDITE PACKET REQUIRED TO BE FILLED OUT FOR ALL JOBS (EXISTING SYSTEMS, ONLY INCLUDE OUR SYSTEM)

Site

ALL STRUCTURES ON THE SITE PLAN MUST BE LABELED AND DIMENSIONED

Roof Plan


Attachment Detail


Electrical Diagram

EXISTING SYSTEMS

  • PROVIDE COMBINED KW SIZE FOR BOTH SYSTEMS


SUB PANELS / RELOCATING LOADS:

  • PROVIDE PANEL SCHEDULE
  • IF RELOCATING LOADS 6' OR MORE, ADD NOTE [RELOCATED LOADS TO BE PROVIDED WITH AFCI BREAKER(S)]
Electrical Diagram Notes


Label Page

FOR BOTH RAPID SHUTDOWN COMPLIANT SYSTEMS AND NON-COMPLIANT PV SYSTEMS, THE PLACARD MUST INDICATE THIS.

  • Placard must show dotted lines around non-RS panels and state that [MODULE TO REMAINED POWERED AFTER SHUTDOWN, NON-RAPID SHUTDOWN COMPLIANT]
Custom Placards Required
1
Placards Notes
  • If there are both Rapid Shutdown compliant (proposed) and non-compliant PV (existing) systems installed. The placard must reflect this as per California Electrical Code (CEC) 690.56(C)(2)
  • The Site Placard must reflect that the existing PV system is NOT Rapid Shutdown compliant. Consult CEC 690.56(C)(2). Placard must show dotted lines around non-RS panels and state that they “remain energized after rapid shutdown.” CEC 690.56(B), 690.56(C)(2), 705.10, 706.11(A)

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Santa Ana (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.