City of Poway (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 2
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes - 10kW+
- Wet Stamps Required
- None
- Structural Calculations Required
- Yes - 10kW+
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 5
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
ESS disconnect required within 6ft of MSP on same wall and not blocked by walls/gates/etc
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
Mark MPU as (E) existing on plans
Add “CAUTION: MULTIPLE SOURCES OF POWER.” note on site placard
- Cover Page
If performing an MPU, the scope of work on the cover page needs to include this.
- Site
BOS equipment cannot be placed on the front of the home facing the street.
- Attachment Detail
Module Compatibility List or a documentation/certification to verify that the rack system has been evaluated and tested for grounding and bonding with the new solar module
Specification sheets showing the fire class rating/classification. Verify compatibility with the PV solar module.
UL 2703 Listing.
- Electrical Diagram
Three line diagram only.
Breaker tie-in: note that the PV breaker will be placed at the opposite end of the busbar from the main breaker
- Electrical Diagram Notes
All Jobs [New electrical shall be located at least three (3) feet from gas meter or gas shut off valves. CPC1208.7.1; CEC 110.26. // Grounding electrode conductor shall be sized per CEC 250.66]
All Jobs [The AIC rating for the main breaker and solar breaker shall have an equal or greater AIC ratings than the existing breakers CEC 690.13(E). or by other means of showing the PV system is rated for the available fault current.]
All Jobs [The minimum distance between the conduits located on the roof and the roof surface are greater than 1"]
- Label Page
Each ESS disconnecting means shall plainly indicate whether it is in the open (off) or closed (on) position and be permanently marked "ENERGY STORAGE SYSTEM DISCONNECT."
The disconnecting means shall be legibly marked in the field to indicate the Nominal ESS AV voltage and maximum ESS DC voltage [CEC 706.15(C)(1)]
- Label Page Notes
All Jobs [Marking should be placed on all interior and exterior DC conduit, raceways, enclosures and cable assemblies, every 10 feet, at turns and above/or below penetrations and all DC combiner and junction boxes. // 2025 CEC 690.31(D)(2)]
- Custom Placards Required
- 1
- Placards Notes
See (7) Inspection Guide_201706291256135953.docx Page 7-8
- Non Standard Planset Requirements
- Single Line Diagram
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
Per City, GM's do not require fencing UNLESS the yard is not fenced. However, the setbacks are different for each property because it is a wildlife habitat and there are some "NO BUILD ZONES" Include full parcel/property on site plan
- Setback Front Yard
- 10
- Setback Back Yard
- 10
- Setback Side Yard
- 10