City of Oakland (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 45196
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restriction Notes
Solar Exclusions: Trenching, Existing System, battery
- SolarAPP+ Restrictions
- Existing Systems,Trenching,Derate
- How Many Plansets Required
- 2
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- None
- Structural Calculations Required
- No
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category B
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- \- _**Are structural calculations required for roof mount or ground mount solar?**_ Not for roof mounted if the panels will eliminate the live load. and it's not a ballasted system. Ballasted and elevated systems including ground-mounted will require calculations. \- _**Are load calculations required for de-rate of main breakers?**_ (or any other requirements). The inspectors typically require this. The calculations are not required to be submitted when applying for the permit. but should be made available at the site. \- _**Is a structural observation report required?**_ Not usually but it may be required for ground mount or elevated system depending on the complexity of them.
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
No published information about battery placement. If battery system, include this note on ELD: Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
* Please fill out the solar checklist, attached in file section below, file name: 'Solar Checklist_City of Oakland'
For flat roofs where the building is mixed use and not a house or duplex the CRC is not applicable to this building. As such, the code requires a minimum of 4' access path along all roof edges.
- Attachment Detail
All roof penetrations need to be flashed properly
- Electrical Diagram
120% allowed
- Custom Placards Required
- 1
- Placards Notes
Permanent placards required from placard sheet of approved plans
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
Soil Class: Clay