City of Malibu (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching,Derate
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- None
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
California Residential Code R324.7
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
Standard
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
- Panel Schedule Required
- All Projects
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
- Provide backup load calculations
- Provide panel schedule for the main service panel
- Provide load calculations that match the panel schedule
- Add note to cover page stating all work shall comply with the most current Los Angeles County Fire Code
- Provide a scope of work on the title page for the ESS including number of stories, occupancy type, total number of ESS units, ESS models, and ESS locations
- Use the Fire Hazard Severity Zone website to determine if the project is in a Fire Hazard Severity Zone
- Add site plan note (if applicable) stating the project is not located in a fire hazard severity zone or state responsibility area and is exempt from CRC R377.6.2 and CBC 706A.2 requirements
- Provide 36-inch wide emergency escape and rescue pathways to qualifying doors and windows above the roof plane per CFC 1204.2.2
- No electrical components associated with the battery-integrated PV system shall be located above the roof decking within required emergency pathways
- Compliance with emergency pathway requirements shall be subject to inspection by the fire code official, including lifting roof tiles as required
- Provide a garage floor plan if applicable
- When ESS is installed inside a garage, the attached garage must comply with all applicable codes, standards, and the manufacturer’s installation manual, including fire protection features and alarm/detector requirements when available
- Exterior ESS units shall not be installed within 5 feet of windows, doors, or HVAC vents
- ESS units shall be installed no less than 3 feet from other ESS units
- Electrical Equipment Elevation (EEE) page is required
- Add note to EEE and SLD stating the battery is installed at least 5 feet away from doors and windows
- Add note to ELD stating the ESS circuit breaker shall be secured by an additional fastener per section 408.36(D)
- Circuit breaker and fastener must be manufactured by the same manufacturer
- All secondary power sources must include breaker hold-down kits
- Provide Cutler-Hammer or Square D breaker hold-down kit documentation
- Provide power source disconnect schedule including disconnect number and type
- Identify PV rapid shutdown disconnect as disconnect 1 of 2
- Identify ESS disconnect as disconnect 2 of 2
- Provide fire department electrical building placards for disconnects 1 of 2 and 2 of 2
- Battery backup disconnects must be clearly identified for emergency personnel
- ESS disconnect must be within 6 feet of the main service panel, on the same wall, and not blocked by walls, gates, or obstructions
- Clarify how emergency services will shut down all PV and battery systems
- Provide an accessible emergency service disconnect within 3 feet of the main service panel that shuts down all solar and battery systems
- Emergency disconnect must comply with code sections 110.25, 705.22, 705.23, 705.31, 706.7, and 706.30
- If ESS is installed in a basement, garage, or more than 6 feet from the main service panel, provide an ESS emergency shutdown plunger switch
- Comply with California Fire Code 1206.2 requirements including room layout, fire-resistance-rated assemblies, battery quantities and types, manufacturer specifications and ratings, energy management system details, signage, fire extinguishing systems, smoke detection systems, and rack storage with seismic support
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
All work shall comply with 2020 Los Angeles County Residential Building Code ; 2020 Los Angeles County Electrical Code, California Residential Code, California Electrical All work shall be performed by a California Licensed Solar Contractor (C-46) or a California Licensed Electrical Contractor (C-10) Local utility provider shall be notified prior to use and activation of any solar photovoltaic system installation
- Cover Page
All Jobs [S5 CLAMPS TO BE TORQUED TO CORRECT SPEC PRIOR TO ARRAY INSTALL]
- Electrical Diagram
Standard
- Label Page
See attached file (electrical Power Source Disconnect Placarding System)
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim