City of Lemon Grove (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Testing
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching,MPU,MPU,Derate,Derate
- How Many Plansets Required
- 2
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- None
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Center
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
PE Requirements; SE digital stamps on corresponding PV pages and PE Letter / Structural Calcs. Engineer cannot use the blank square in the title block to apply their seal. The AHJ wants this left open for their plan reviewer to place their stamp.
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- PV Breaker,Load Side Taps,Line Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 1
- ESS Notes
- ESS disconnect required within 6ft of MSP on same wall and not blocked by walls/gates/etc.
- Single Line Diagram and Site Placard - Show the location of the ESS disconnecting means (lockable) within sight from (50ft - Article 100 definitions) and compliance with 706.15(A)(1)(2)(3) CEC.
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
AHJ requires that Occupancy Type (R2 or R3) and Construction type VA/VB (5A/5B) Be noted on plans. We must provide a 3 (tall) by 2 (wide) blank space designated For City Stamps on all PV sheets in the same location of the title block.
- Site
Heartland Fire & Rescue correction (a past project): Is building sprinklered or non sprinklered? construction type? (typically type V [wood construction]) Identify total roof Sq footage total array Sq footage
- Electrical Diagram
BATTERY JOBS: Clarify if battery is time of use or for backup loads. Add disconnect at battery
For SEEB Projects: Utilize 100A AC Disconnect for 63A CHINT breaker.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim