City of Half Moon Bay (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 2
- Revision Required
- 0
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- None
- Structural Calculations Required
- Yes - 10kW+
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category B
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- Structural is required for systems over 10kW
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,PV Breaker,Line Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
No published information about battery placement. If battery system, include this note on ELD: Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).
Provide attachment details of ESS to the structure.
Include Panel Schedule of backup loads
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Demonstrate compatibility between the racking system and the modules. This can typically be obtained from the racking installation manual.
- Cover Page
Provide a complete scope of work on the cover sheet
Provide the square footage of both floors (if applicable) and garage.
- Site
Site plan must show conduit runs with conductor call outs, inverters, disconnects, panel boards, distribution equipment, and structures such as carports.
- Roof Plan
Detail the fire access pathways to all arrays.
- Electrical Diagram
Standard
- Custom Placards Required
- 1
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim