City of Gilroy (CA)
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 44782
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching,Derate
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes - Derate
- Wet Stamps Required
- None
- Structural Calculations Required
- No
- Ee Stamp Notes
EE stamp needed for Main Breaker Derates
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category B
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- Structural Calcs: Only needed if it's an elevated mount, not needed for flush mounts.
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,PV Breaker,Meter Adapter,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
120% rule allowed per CEC 705.12(B)(2)(3)(d) - 1/17/20 KDA Line and load side taps are allowed, we need to provide cut sheets.
If EV charger is included, include a set of EV charger only plans
- Electrical Diagram
120% rule allowed per CEC 705.12(B)(2)(3)(d)
- Custom Placards Required
- 1
- Placards Notes
Hard Stickers and Placards for every job
Ground mount
- Ground Mount Fencing Required
- No