City of Fortuna (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 45112
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching
- How Many Plansets Required
- 3
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 85
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,PV Breaker,Load Side Taps,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
For Shade structures, MAX height is 15'. anything over will not be accepted] AHJ complies with all current codes.
- Site Notes
All Jobs [Conduit must be run internally per Fortuna Fire Protection District Ordinances]
- Roof Plan
Conduit must be run internally per Fortuna Fire Protection District Ordinances. Show where the conduit will be run and specify that it will be internal.
- NO ROOF CONDUIT. IT MUST BE RUN THROUGH THE ATTIC
- If vaulted roof, roof top conduit is fine
- Roof Plan Notes
All Jobs [Conduit must be run internally per Fortuna Fire Protection District Ordinances]
- Electrical Diagram
Standard
- Custom Placards Required
- 1
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
For GM's, 15' back yard setbacks, 10' front yard setbacks and 5' side yard setbacks.