City of Encinitas (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 45180
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching,MPU,Derate
- How Many Plansets Required
- 3
- Revision Required
- 1
- New Planset Required For Module Swap
- 1
Stamps
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Demonstrate a 36" pathway for each plane with a PV array.
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- * STRUCTURAL CALCS ONLY FOR GROUND MOUNT
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,PV Breaker,Line Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Accepts 9540a, reduced battery spacing
ESS disconnect required within 6ft of MSP on same wall and not blocked by walls/gates/etc
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
AHJ wants us to provide a filled SOLAR PV STANDARD PLAN SIMPLIFIED CENTRAL/STRING INVERTER SYSTEMS SOLAR PHOTOVOLTAIC ROOFTOP INSTALLATIONS 10 KW OR LESS, ONE- AND TWO-FAMILY DWELLINGS - All future projects must include this packet. ROOF MOUNT: Needs a diagram showing the elevation of the house from the ground to the roof and then from the ground to the top of the panel Include on plans basic wind speed of 110MPH (3-second gust) and wind exposure for the site. ROOF MOUNTED SYSTEM DO NOT REQUIRE STRUCTURAL ELEVATION IS NEEDED. DIMENSIONS FROM GRADE TO TOP OF ROOF AND FROM GRADE TO TOP OF MODULE AHJ Allows Ballasted systems
- Site
If installing on a duplex, the site plan should clearly show property lines dividing the homes and notate the address of each home so that there is no confusion which address is being installed on and that no panels are being placed on a neighbor's roof.
- Electrical Diagram
Standard
- Custom Placards Required
- 1
- Non Standard Planset Requirements
- BOS Elevation
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
* Ground Mounts require structural calcs * Ground Mounts: 5' side yard setback from property line. Setback requirements are uploaded below. * NOTE ON SITE PLAN: NO VEGETATION TO BE WITHIN 10 FT OF GROUND MOUNT * STRUCTURAL CALCS ONLY FOR GROUND MOUNT