City of Elk Grove (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 45204
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching
- How Many Plansets Required
- 2
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- None
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- ESS Notes
- WE SHOULD AVOID BATTERIES IN GARAGE AT ALL POSSIBLE. THIS SHOULD BE LAST RESORT AND ONLY IF THE PROJECT WILL BE DQED BY HOMEOWNER.
- Batteries cannot be mounted in the garage unless the customer has EXISTING fire sprinklers installed in the garage.
- Show location of door and window opening in relation to ESS. (This includes SolarApp qualified projects)
- Show 3’ distance between ESS units. (This includes SolarApp qualified projects)
- Battery [ESS installed outdoors or on the exterior side of exterior walls shall be located not less than 3' from doors or windows directly entering the dwelling unit. // Individual ESS units shall be separated from each other by at least 3 ft. unless large scale fire testing documentation is provided for reduced spacing.]
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes
Plan set
- Plan Set Requirements
- ALL PROJECTS: Designer signature or Greg's signature must be on each page of the plans.
- EV CHARGING: Include cut sheets for EV charger. Fill out EV checklist in files below.
- BATTERIES: Batteries cannot be mounted in the garage unless the customer has EXISTING fire sprinklers installed in the garage..
- Cover Page Notes
BATTERY [INSTALLATION SHALL COMPLY WITH NFPA 855, 2023 EDITION // SYSTEM SHALL BE UL 9540 LISTED. // ESS LISTED AND LABELED SOLELY FOR UTILITY OR COMMERCIAL USE SHALL NOT BE USED. // INSTALLING CONTRACTOR SHALL PROVIDE A COPY OF THE MANUFACTURER'S INSTALLATION, OPERATION, AND MAINTENANCE INSTRUCTIONS. // INSTALLING CONTRACTOR SHALL VERIFY THE SYSTEM IS INSTALLED ACCORDING TO APPROVED PLANS AND THE MANUFACTURER’S INSTRUCTIONS AND OPERATING PROPERLY. // INSTALLING CONTRACTOR SHALL PROVIDE TRAINING ON THE PROPER OPERATION AND MAINTENANCE OF THE SYSTEM. // INSTALLING CONTRACTOR SHALL PROVIDE A LABEL ON THE SYSTEM CONTAINING CONTACT INFORMATION FOR QUALIFIED MAINTENANCE AND SERVICE PROVIDERS. // ESS SHALL BE SEPARATED FROM EACH OTHER AND DOORS/WINDOWS BY MINIMUM 3 FEET. // FOR INTERIOR INSTALLATIONS, THE GARAGE WALLS/CEILING SHALL BE PROTECTED WITH MINIMUM 5/8" TYPE X GYPSUM BOARD. THE DOOR LEADING INTO THE LIVING SPACE SHALL BE SOLID WOOD CORE AND SELF-CLOSING. // SYSTEMS CONNECTED TO THE UTILITY GRID SHALL USE INVERTERS LISTED FOR UTILITY INTERACTION. // ESS INSTALLED IN LOCATIONS SUBJECT TO VEHICLE DAMAGE SHALL BE PROVIDED WITH APPROVED BARRIERS. // RESIDENCE SHALL BE PROVIDED WITH INTERCONNECTED SMOKE ALARMS. // PANELS AND MODULES SHALL NOT BE LOCATED BELOW AN EMERGENCY ESCAPE AND RESCUE OPENING. A MINIMUM 36 INCH WIDE PATHWAY SHALL BE PROVIDED FOR ALL SUCH OPENINGS. // ESS THAT EMIT TOXIC GASES SHALL NOT BE USED IN R-3 OCCUPANCIES. // ESS THAT GENERATE HYDROGEN OR OTHER FLAMMABLE GASES SHALL BE PROVIDED WITH MECHANICAL VENTILATION IN ACCORDANCE WITH CFC 1207.6.1]
- Site
SOLARAPP:
- Site Plan will need to include all components corresponding to the legend as leaders for SolarApp EZ Plans per Fire Department review requirements.
- Need to include the entire site address on the site placard.
- include the Scope of Work on the Cover Page.
- Make sure for ESS projects the cover page note is still included (Installations shall comply with...) and the Site plan ESS notes are included as well.
- EV CHARGING: Must show location of EV Charger.
- Site Notes
Battery [ESS installed outdoors or on the exterior side of exterior walls shall be located not less than 3' from doors or windows directly entering the dwelling unit. // Individual ESS units shall be separated from each other by at least 3 ft. unless large scale fire testing documentation is provided for reduced spacing.]
- Electrical Diagram
- 120% rule allowed per CEC 705.12(B)(2)(3)(d)
- Only single line diagram required, not three line.
- SPD Required
- EV CHARGING: Show EV Charger and its POI.
- Electrical Diagram Notes
Battery [If ESS is present, ESS shall not be within 3' of openings into dwelling unit]
- Label Page Notes
- Custom Placards Required
- 1
- Placards Notes
- Full address must be on site placard
- Non Standard Planset Requirements
- Single Line Diagram
- Non Standard Revision Requirements
- Include a point‑by‑point response letter listing each requested change and where it appears on the plans.
- Mark every change on the drawings using clouds or delta symbols.
- Incorporate all revisions requested by other agencies.
- For each change, cite the specific detail, specification, or calculation that demonstrates compliance.
- Clear, complete responses will speed up the re‑check process.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
- Provide trenching details on the plans, showing conduit depth, backfill material, and placement of electrical warning tape
- On sheet PV‑03, indicate a 10 ft clear, brush‑free zone around the array (per CRC R324.7.2)