City of Chino Hills (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Not accepted
- Date SolarAPP+ Accepted
- 45208
- Any SolarAPP+ Restrictions
- 1
- How Many Plansets Required
- 3
- Revision Required
- 1
- Rough Inspection
- Fire Inspection
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- None
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category B
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 48
- Structural Notes
When covering more than 10% of the roof, structural is required. When covering less than 10% of the roof: 48" OC staggered spacing: structural **_is not_ **required 72" OC spacing: structural **_is_ **required
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Line Side Taps,Meter Adapter,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Interior installation: Provide floor plan of garage with location of ESS Demonstrate vehicular impact protection (unless location of ESS exempts it from the requirement) Provide interconnected heat alarm in garage. Call out on plans. 2 car garages will require 2 parking spaces (20x20) clearance on floor plan. provide approved smoke/heat alarm in garage/over the battery. Add note to garage floor plan, elevation drawing, and ELD: smoke/heat Alarm shall be hardwired, battery back up and interconnected
please see redlines on SLD pertaining to heat alarm. On garage illustration they want the heat detector hardwired to be illustrated. they want to see the width dimension for the battery, how far it's protruding from the wall
2/6/24 show battery distance protruding from wall (on garage illustration)
heat alarm required hard wired and interconnected (show on garage illustration and SLD)
- Separate ESS Disconnect Required
- Local Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
Bus certs are NOT accepted Font size must be min 1/8 height point size. Cannot use colored fonts.
- Cover Page
ALL JOBS ARE NOT SOLAR APP QUALIFIED
- Roof Plan
STANDARD
- Attachment Detail
Use 48" OC staggered spacing so that structural **_is not_ **required
- Electrical Diagram
When relocating loads, specify which loads are being relocated. Center-fed panels: show existing loads
- Custom Placards Required
- 1
Ground mount
- Ground Mount Fencing Required
- No