City of Beaumont (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 44571
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching
- How Many Plansets Required
- 3
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes - 10kW+
- Wet Stamps Required
- Digital Electrical,Digital Structural
- Structural Calculations Required
- Yes - Battery,Yes - Existing PV
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
For each roof plane with a solar pv array, a pathway of not less than 36 inches wide shall be provided from the lowest roof edge to the ridge on the same roof plane as the solar pv array, on an adjacent roof plane or straddling the same and adjacent roof plane
Structural & loads
- Wind Speed
- 130
- Wind Notes
Exposure Category C Show wind zones 1,2,3 on plans
- Snow Load
- 5
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- Standard
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
- Battery projects require special placards
- ESS disconnect must be within 6 ft of the main service panel, on the same wall, and not blocked by walls, gates, or other obstructions
- ESS cannot be installed in direct sunlight or in temperatures exceeding 122°F per the installation manual
- Provide UL 9540 compliance documentation (or equivalent) showing the specific ESS model
- ESS disconnecting means must be separate from the PV system and located between the inverter and the ESS
- Provide structural design and construction details for ESS supports and anchorage
- When installed in a garage, provide impact protection per CFC
- A listed heat alarm must be installed where smoke alarms are not allowed and must be interconnected with existing smoke alarms per CFC
- Battery and lockable disconnect must be installed inside the garage
- Provide cut sheet for a CSFM-approved rate-of-rise heat detector
- Show heat detector location on plans
- Confirm heat detector is interconnectable with existing smoke alarms
- Separate ESS Disconnect Required
- Local Disconnect,ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
- Cover Page
- Provide signature for dig alert
- Site
- Include on site plan the required working clearances in-front of the electrical equipment to the property lines and other obstructions.
- If Inverter is not within 6 ft or line of sight of MSP, a second disconnect is required.
- Site Notes
All Jobs [No new or existing easements, or development-restricted areas exist on the property. // Disconnect shall be on the same side of the fence as the Solar Photovoltaic equipment] MPU [Location of (N) Electrical Service Equipment must be approved by the Utility Company]
- Roof Plan
- Attachment Detail
- Standard flashing
- Electrical Diagram
- 120% rule allowed per CEC
- Electrical Diagram Notes
All Jobs [CEC COMPLIANT JUNCTION BOX SHALL HAVE A 3/16" (5MM) DRAINAGE HOLE AT THE LOWEST POINT OF THE ENCLOSURE PER UL50 9.7.2 IN ACCORDANCE WITH 7.3.3.3. and CEC 314.15]
- Custom Placards Required
- 1
- Placards Notes
- Plaques must be mechanically attached (self tapers) on MSP & A/C disconnect.
Ground mount
- Ground Mount Fencing Required
- Yes