Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

County of Gila (AZ)

Arizona Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2011
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2011
Fire Code Version
2018 Building Code
Code List

2012 INTERNATIONAL RESIDENTIAL CODE 2012 INTERNATIONAL BUILDING CODE 2012 INTERNATIONAL EXISTING BUILDING CODE 2012 INTERNATIONAL FUEL GAS CODE 2012 INTERNATIONAL MECHANICAL CODE 2012 INTERNATIONAL PLUMBING CODE 2012 UNIFORM SWIMMING POOL, SPA & HOT TUB CODE 2011 NATIONAL ELECTRIC CODE ICC A117.1-2009 ACCESSIBLE AND USUABLE BUILDINGS AND FACILITIES CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
2
Revision Required
1
Rough Inspection
Racking Inspection
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category B

Snow Load
999
Snow Load Notes

Below 4500 ft elevation - 20 PSF roof, 28 PSF Ground Between 4500 - 6000 ft elevation - 40 PSF roof, 57 PSF Ground Above 6000 ft elevation - 40 PSF Roof, 57 PSF ground (See _Gila County Design Criteria_ Document below)

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Structural Calcs required on all projects. Need to show both _**ground** and **roof snow**_ loads on both _ **Plans** and **Calcs**_ When sending to engineer, inlcude the file named _Gila County Design Criteria_ in file section below.

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

NEED GROUND AND ROOF SNOW LOADS ON BOTH PLANS AND STRUCTURAL CALCS OR PLANS WILL BE REJECTED AT TIME OF SUBMITTAL Need live roof snow load AND ground snow load. System with batteries and/or generator: Cut sheet for batteries. 2 copies (Battery conductors must be NEC approved) Cut sheet for battery storage container or racking if applicable. 2 copies Cut sheet and listing for battery charge controller. 2 copies Cut sheet (2 copies) and installation manual (1 copy) for generator and transfer switch. Roof mounted system: (dc ground fault protection required) Signed waiver for installation on an existing building. For new manufactured homes, the Office of Manufactured Housing requires the home's manufacturer be contacted to determine if and how modules may be installed. Provide manufacturer's approval. Roof framing information (mfg trusses, rafter sizes & spacing). Contact office for specific requirements if installation is to be on an existing manufactured home. Weight of array with mounting system in psf and point loads (structural engineering may be required due to excessive psf and/or point loads or if other unique circumstances deem it necessary) Approximate age of building and roofing type (asphalt shingle, clay tile, metal) Installation manual (1 copy) or engineered detail (2 copies) of module support attachment to roof framing members and method of sealing roof penetrations. MODULE SUPPORT/RACKING AND SUPPORT BONDING/GROUNDING

Site

Include the following on site plan: • North Arrow • Parcel # and Address • Street names • Dimensioned lot lines • Setback lines with dimensions to property lines • Locations and dimensions of all existing and proposed structures (include fences) and distances between structures and lot lines • Locations of all washes, ditches, creeks and drainages. • All easements, driveways • Septic systems and leach fields • Locations of all existing and proposed utilities including: o Utility lines and underground piping o Water, electric, and gas meters o Well o Propane tank and distances to property lines and any structures

Electrical Diagram

Standard

Label Page

Map placard must be added to page

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Ground Mount Notes

Ground mounted system: ⌂ Weight of array in psf and point loads including mounting system. ⌂ Detail of engineered or manufacturer’s array support, framing members, foundation posts and footings. 2 copies (footings must meet frost depth requirement) ⌂ Array height above grade noted on plans. ⌂ Energized parts operating at 50 volts or more shall be guarded against accidental contact by approved enclosures.

Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Gila (AZ) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.