City of Phoenix (AZ)

Arizona Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredDigital Electrical,Digital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2024 INTERNATIONAL BUILDING CODE

2024 INTERNATIONAL ENERGY CONSERVATION CODE

2024 INTERNATIONAL SWIMMING POOL AND SPA CODE

2024 UNIFORM MECHANICAL CODE

2024 UNIFORM PLUMBING CODE

2023 NATIONAL ELECTRICAL CODE

2018 INTERNATIONAL FIRE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Date SolarAPP+ Accepted
44733
Any SolarAPP+ Restrictions
1
SolarAPP+ Restriction Notes
  • Ground-mounted systems
  • Ballast System


SolarAPP+ Restrictions
Storage Systems,Existing Systems,Trenching,Historic District,Flood Zone,MPU,Derate,Other
How Many Plansets Required
2
Revision Required
1
Rough Inspection
Flood Inspection
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes - Battery,Yes - Derate,Yes - MPU
Wet Stamps Required
Digital Electrical,Digital Structural
Structural Calculations Required
Yes - Existing PV
Ee Stamp Notes

Strict AHJ: Panel schedule and load calcs must match exactly

Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Flat Roof Setbacks

  • Ensure 3-foot wide perimeter pathways around the roof edges.
  • Include 3-foot wide interior pathways every 150 feet within the array.
  • No need for extra space above panels if there is no ridge 

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates,MPUs,Load Relocation,Battery
Allowed POI
Line Side Taps,PV Breaker,Load Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
75
De Rating Ampacity
0.87
BOS Restrictions


Battery / ESS

Unique Battery Placards Needed
1
ESS Notes

Do this on Site Plan and ELD(s):

  • Call out make and model for all Disconnects.
  • TPW cannot be stacked, need to be at least 5' away from windows/doors
  • ESS to be placed near MSP to reduce conduit runs
  • ESS disconnect to be within 5' of battery
  • Heat detector interconnected with smoke detectors in residence required for ESS installed inside of home/garage.

Add note: "The ESS circuit breaker shall be secured by an additional fastener per section 408.36(D)."

Separate ESS Disconnect Required
Local Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

#NFZ_ALL

Standard Jobs

  • Module spec sheets must show UL 61730 listing
  • Provide spec sheets for all electrical equipment to be installed including MPUs, sub panels, and main breaker enclosures. 
  • Provide manufacturers documentation to clarify system components are listed according to the UL standards to which they apply: UL 2703 for grounding/bonding of rails, mounts, clamps, ground lugs, etc.

 Historic District:

  • AHJ stated the panel can not be in front of house, if the home is in historic district. (See https://www.phoenix.gov/pddsite/Documents/HP/pdd_hp_pdf_00133.pdf for more information)
  • Please use the following link to determine if property is in historic district. Use the Layer list to Identify historic property areas: https://phoenix.maps.arcgis.com/apps/webappviewer/index.html?id=13428321a9f84e95a634be1beab5fe96
  • If we have no options with the layout please provide a letter justifying the layout. The letter must clearly demonstrate the loss of efficiency and savings if the panels are moved to another location or removed entirely. 
Site
  • Disconnect for line-side taps must be located within 10 feet of the service connection point.
Site Notes


Roof Plan
  • If home is in historic district, no modules will be allowed on the front of main residence.
Electrical Diagram

All Jobs:

  • Main breaker must be rated 22k or higher. Only panels not able to account for this is a Square D HOM or Zincso, if this panel is existing and existing main is only rated for 10K, we will need to perform a MPU to a panel that is 22k rated at Construction Review stage (A ConnectDER can also satisfy this requirement). All other panel brands, we will be able to source a 22k rated breaker.
  • Provide minimum conductor length on the electrical diagram. (See document below named "City of Phoenix - minimum conductor length" for reference) Information is conditional on size of wire, and utility.
  • If PV back feed is over 60A, then use a fused disconnect with Class J fuses. This will satisfy the minimum conductor length requirement. Include a note "Fused disconnect with Class J fuses to limit AFC to less than 10000"
  • PV breaker shall be either 22K AIC fully rated or a listed series, unless Fused disconnect with Class J fuses is used
  • If you are derating, derated breaker shall be either 22K AIC fully rated or a listed series, note must be present on line diagram
  • If using a lineside tap, the OCPD must be within 10ft of the service connection point. Notate the distance to OCPD from main service.
  • LST require a bonding jumper at the fused disconnect
  • LST: notate the following: DISCONNECT FOR THE LINE-LIDE TAP MUST BE LOCATED WITHIN 10 FEET OF THE SERVICE CONNECTION POINT.

For Load Centers/Sub Panels

  • Any panels with conductors rated 100A or more, Panel will need a 22k rated main breaker, and all branch breakers need to be listed series rated
  • Provide a panel schedule for any relocated loads
  • Under 100A, install 22k rated breakers in the load center/sub
  • Load center breakers to either be 22K fully rated or series rate 22/10 with a 22K rated panel MCB, unless conductor length to limit AFC is provided.

FOR LOAD CONTROLLERS

  • On the permit plan set, remove the load controller from the plans completely (TLD and layout). We are doing this on all City of Phoenix jobs, as they are very difficult to work with when it comes to the load controllers. The LC will still be installed, just won't be shown on the plans.
  • On the utility copy of plans, show the Load Controller
  • ADD NOTES TO TLD: MINIMUM CONDUCTOR LENGTH TO BE #' FROM AC DISCONNECT TO PV BREAKER PER ARTICLE 110.9 & 110. (VARIES - Verify footage on fault current document below) CANNOT USE "~" SYMBOL WHEN REFERENCING CONDUCTOR LENGTH

ESS:

  • Always provide panel schedule
  • Include the following note: The ESS circuit breaker shall be secured by an additional fastener per section 408.36(D).

MPUs:

  • Provide spec sheet for main panel. The part number must be listed on the line diagram that matches the spec sheet. Load Calcs needed

Existing Systems:

  • New system must be separate from existing system

Feed Thru Lugs

  • Provide an actual make/model for the kit

Derates

  • Derates require a panel schedule
Electrical Diagram Notes

All Jobs [Where raceways or cables are exposed to direct sunlight on or above rooftops, raceways or cables shall be installed a minimum distance above the roof to the bottom of the raceway or cable of 23 mm (7⁄8 in.). Where the distance above the roof to the bottom of the raceway is less than 23 mm (7⁄8 in.), a temperature adder of 33°C (60°F) shall be added to the outdoor temperature to determine the applicable ambient temperature for application of the correction factors in Table 310.15(B)(2)(a) or Table 310.15(B)(2)(b) // PV BACK-FED BREAKERS SHALL BE EITHER 22K AIC FULLY RATED OR A LISTED SERIES RATED BREAKER WITH THE MAIN OCP FOR 22/10K FOR 200 AMPS THROUGH 400AMPS, SINGLE PHASE, 240 VOLTS. 2017 NEC ARTICLE 110.9, AND ARTICLE 240.86(B). // ALL EQUIPMENT TERMINATIONS SHALL BE RATED MINIMUM 75 DEGREE C. 2017 NEC ARTICLE 110.24(C) // ALL CONDUCTORS NOT UNDER ARRAY ARE TO BE IN CONDUIT MINUMUMM 7/8 " ABOVE ROOF WITH PROPERJ-BOXES AT EACH END PER 690.31a] Derates [Derated breaker shall be either 22K AIC fully rated or a listed series]

Battery [The ESS circuit breaker shall be secured by an additional fastener per section 408.36(D)]

Custom Placards Required
0
Placards Notes

Custome Placards only required on select projects.

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes

As long as there is 3ft from the house. TR 7/15